Key Stats for Cipher Digital Stock
- Current Price: $13.52
- Change Since June 30, 2026: -44.8%
- Street Target (Mean): ~$30
- Implied Upside to Street Mean: ~125%
- 52-Week High (Intraday): $30.14
Now Live: Discover how much upside your favorite stocks could have using TIKR’s new Valuation Model (It’s free) >>>
What Happened?
Cipher Digital (CIFR) closed at $13.52 on October 9, down 44.8% from its $24.50 close on June 30. Over the same stretch, consensus revenue for 2027 slipped only about 3%. The latest leg began with a 6.06% drop on October 7 and deepened on October 8, when, according to Benzinga, rising Treasury yields, a falling Bitcoin price, and a Financial Times report on OpenAI’s revenue run rate weighed on data center and AI infrastructure stocks. Cipher’s investor relations materials show that rates matter less for what it already owes than for what it needs next.
Fixed-Rate Debt Covers the Original Budgets
Cipher carried just over $6 billion of corporate and project debt as of June 30. On the August 4 call, CFO Greg Mumford said the “committed funding that we already have in place for our existing projects is fixed rate,” calling it “5-year fixed rate debt.” Three project bond deals fund Cipher’s contracted obligations at Barber Lake, Black Pearl, and Stingray through completion, so October’s yield spike leaves those costs unchanged until they are refinanced.
New capacity is where rates bite. Mumford also said Cipher could handle the sites in front of it without tapping equity markets, but a deal of several hundred megawatts to a gigawatt would need an equity contribution, and “there may be a situation down the road where we do need equity.” Higher borrowing costs make that hurdle steeper.
CEO Tyler Page said 477 megawatts are potentially available in 2027 outside Texas’s interconnection batch process, at Odessa, Reveille, and Ulysses. “I expect that they will all be signed,” he said. Odessa runs on a clock: first megawatts in 2027 “will depend on getting a lease done in the coming couple of months,” Page said on August 4. Cipher had not announced an Odessa lease as of October 9, and the site’s power contract runs through the end of July 2027.

See historical and forward estimates for Cipher Digital stock (It’s free!) >>>
Barber Lake Added a Second Decade, and a Cost Bill
Black Pearl delivered its first capacity in early August, two months ahead of schedule, and rent began. At Barber Lake, Page said on August 4 that Phase 1 was on track for October rent with 100% of equipment secured. On September 25, Cipher amended its Fluidstack lease and announced a binding commitment from an unnamed AI lab to lease the site for a second 10 years under a separate lease to come. Contracted revenue rises above $9 billion, but tenant change orders spread hall deliveries from Q4 2026 into Q1 2027. First rent is still expected in Q4, and Cipher says it is on track with the revised schedule.
Cipher bears the first $359.3 million of costs above the original budget, and the tenant reimburses half of any excess beyond that over 20 years. The added revenue starts a decade out, while any overrun up to that threshold is a cost Cipher funds during construction. On August 4, Page said current builds were “running at the contingency level given that inflation.”

See how Cipher Digital performs against its peers in TIKR (It’s free!) >>>
What the Street’s ~$30 Target Asks For
- Street Target (Mean): ~$30 (~$33 on June 30)
- Street Target Range: $18 to $59 ($69 high on Sept. 30)
- NTM EV/EBITDA: 34x (66x on June 30)
- Consensus Revenue: ~$219 million (2026), ~$850 million (2027)
See analysts’ growth forecasts and price targets for Cipher Digital stock (It’s free!) >>>
Both Holds appeared after June 30, yet the $18 low still sits about 33% above the October 9 close. The multiple was halved partly because the forward window now captures more rent, with NTM EBITDA consensus rising from around $212 million on June 30 to around $306 million on September 30. Cipher sits just below TeraWulf (WULF) at 35x, but about double Nebius Group (NBIS) at 17x and four times IREN (IREN) at 8x.
The October 9 enterprise value of $10.39 billion is about 13 times the roughly $793 million of average annualized net operating income management projected on August 4 for its three leases from October 2026 to September 2036, a figure set before the Barber Lake amendment. That math holds only if rent arrives on time. Second-quarter revenue of $24.84 million missed estimates by 21.71% as mining was decommissioned at Black Pearl, and shares fell 15.65% on August 4.

Cipher’s third-quarter update, which Yahoo Finance estimates for early November, is the next checkpoint. First Barber Lake rent inside Q4, plus a signed lease on any of the 477 megawatts financed without new equity, would support the Street’s math. Another Barber Lake delay, or an equity raise to fund a new build, would put even the $18 low target in question.
See what stocks billionaire investors are buying so you can follow the smart money with TIKR.
So what is Cipher Digital stock actually worth?
TIKR lets you forecast the future price of any stock in less than a minute. Just enter a few assumptions into TIKR’s valuation model and see what Cipher Digital could be worth. Start from Wall Street consensus estimates, or adjust the inputs to reflect your own view of the business. It’s free to use.
Analyze Cipher Digital on TIKR Free →
Disclaimer:
Please note that the articles on TIKR are not intended to serve as investment or financial advice from TIKR or our content team, nor are they recommendations to buy or sell any stocks. We create our content based on TIKR Terminal’s investment data and analysts’ estimates. Our analysis might not include recent company news or important updates. TIKR has no position in any stocks mentioned. Thank you for reading, and happy investing!