Key Takeaways
- Riot Platforms signed a 15-year, 910 MW lease for its whole Corsicana campus worth about $28 billion, lifting contracted data center revenue to roughly $38 billion.
- Bitcoin mining revenue fell 28% to $116.0 million on a lower bitcoin price, while engineering revenue more than doubled to $47.0 million.
- Riot funds about $2 million per megawatt itself, and tenant reimbursements depend on non-recourse project debt that it still has to arrange.
- The first 400 MW is due in September 2027, and the fourth quarter report, expected in February, should show how the financing is taking shape.
Riot Platforms (RIOT) just signed the biggest lease in its history. The bitcoin miner leased its entire Corsicana, Texas campus to a frontier AI lab for 15 years. Its value is about $28 billion over the initial term.
That same tenant signed Riot’s 191 MW Rockdale lease in August, and CNBC confirmed it is Anthropic. Add Advanced Micro Devices (AMD), which already rents 25 MW at Rockdale. Together, Riot now has 1,151 MW leased and roughly $38 billion of contracted data center revenue.
The timing matters. Because bitcoin fell, Riot’s mining revenue dropped 28% to $116.0 million in the third quarter. Similarly, MARA Holdings (MARA) saw total revenue drop 35% under the same pressure.
Jefferies upgraded the stock to Buy on November 10 because Corsicana alone could be worth about $16 a share.
Corsicana is a landlord deal
Riot delivers the land and power infrastructure, plus the powered pads. Meanwhile, the tenant installs, owns and runs the compute, and power costs pass straight through.
The key terms:
- About $1.8 billion of average annual rent, or roughly $54 billion with both five-year extensions
- Delivery of 400 MW in September 2027, 200 MW in January 2028 and 310 MW in July 2028
- Rent due on all 910 MW regardless of utilization
The quarter itself showed a business halfway through a change. Total revenue rose about 1% to $181.4 million, as data center and engineering sales covered the mining slide…

Engineering stood out, since third-party demand for custom electrical equipment lifted it to $47.0 million from $19.1 million.
The rent dwarfs mining
Scale is the obvious draw. At $1.8 billion a year, Corsicana’s average rent is about 2.5 times Riot’s annualized third quarter revenue.
Margins make it better. Riot estimates a 99% NOI margin because the tenant bears substantially all operating costs. CEO Jason Les said in the release that “the structure of this new lease matters as much as the scale.”
Capital explains why. Corsicana costs about $6 million per IT MW, or $5.5 billion in total. That is roughly half the capital of a typical Tier 3 build, and Riot carries only part of it. Jefferies puts a typical data center at $11 million to $15 million per MW.
So what does that do to the earnings outlook?

Corsicana is about three times the size of the $9.1 billion Rockdale lease, so forecasts have plenty to absorb.
TIKR tracks 22 analysts on Riot Platforms. How many say “Buy”?
See the full breakdown of Buy, Hold, and Sell ratings on Riot Platforms, along with Wall Street’s revenue and earnings estimates, all in one place. More than 500,000 investors use TIKR to research stocks like this one. See Riot Platforms’ Analyst Ratings
Bitcoin is funding the build
Riot has turned its bitcoin into a funding source. It sold 20,264 coins for about $1.5 billion in the first nine months of 2026, mainly for data center development. The company raised no equity this year.
That left $950.2 million in cash and bitcoin, including only 2,418 coins. Mining itself is underwater after depreciation. Each bitcoin cost $78,805 to produce on that basis, while the average price was $70,855.
Here’s where the balance sheet stands heading into the build.

Riot funds about $2 million per MW itself. The tenant reimbursements, however, should come from non-recourse project debt sized to the rent. If that debt isn’t available on comparable terms, the tenant pays and recovers it through rent credits.
My take: Corsicana is the best structured miner lease I’ve seen, because Riot gets paid on every megawatt while the tenant carries most of the risk. Still, no Corsicana rent arrives before late 2027. So I’d want the project financing signed before treating $28 billion as banked.
Riot’s fourth quarter report, expected in February, should show whether that debt is taking shape.
So what is Riot stock actually worth?
TIKR lets you forecast the future price of any stock in less than a minute. Just enter a few assumptions into TIKR’s valuation model and see what Riot could be worth. Start from Wall Street consensus estimates, or adjust the inputs to reflect your own view of the business. It’s free to use.
Disclaimer:
Please note that the articles on TIKR are not intended to serve as investment or financial advice from TIKR or our content team, nor are they recommendations to buy or sell any stocks. We create our content based on TIKR Terminal’s investment data and analysts’ estimates. Our analysis might not include recent company news or important updates. TIKR has no position in any stocks mentioned. Thank you for reading, and happy investing!